CO2NTESSA
Location: | Croatia |
Companies / organizations involved: | Nexe |
What elements of the CCS chain are included in the project: | capture |
EU funding or PCI status: | |
Planned start date: | 2029 |
Planned volumes: | >0.7 Mtpa (capture) |
Capture: | Capture: oxyfuel tech at cement plant in Croatia; Transport: pipeline |
Source of captured CO2: | cement |
Transport mode: | pipeline |
Planned storage: | |
Current stage: | project documentation in progress |